Case Study - How to protect a jetty or pier from an oil spill

Background:

Our client based on the Mediterranean Coast has a fuel jetty and needed a permanently installed oil spill response solution that can be deployed and operated easily by 1 or 2 personnel.

The client required a system that could adjust automatically to the large tidal range.

Objective:

To provide a complete boom system to be rapidly deployed prior to fuel transfer operations taking place.

The system must be able to cope with changing sea levels and conditions and need minimal operating personnel. It must be possible to leave the boom system permanently located at the jetty and in the water ready for use.

Solution:

The system supplied consisted of 4 Foam Filled Sentinel Booms with fixed VikoSeal hammerheads mounted mid-way on the outermost booms. This created a Primary Containment Zone of approximately 30m x 5m.

The fixed booms were installed under the Jetty connecting to the piles with slider mechanisms to allow the boom to rise and fall with the tide and swell.

The sliders are attached to the piles using stainless steel bands that require no modification to the piles, making them ideal to retrofit to existing installations.

The VikoSeal booms integrated with the fixed boom can be raised when not in use and lowered into position once the vessel is alongside and prior to loading/unloading operations commencing.

Case Study 9 Image 1c              VikoSeal boom         Foam filled Sentinel boom on sliders            VikoSeal boom


Case Study 2                                                       Installed permanent boom system

 